Marathon Petroleum Corp.’s Trans-Foreland Pipeline Co. unit wants more time to convert the Kenai LNG export plant in Alaska into an import terminal, U.S. energy regulators said on July 11.
A Federal Energy Regulatory Commission (FERC) notice said that Trans-Foreland last week sought an extension until December 2025 to complete the facility.
FERC approved Trans-Foreland’s request to build the plant in December 2020 and gave the company until December 2022 to place it into service.
Trans-Foreland said it has yet to make a final investment decision to build the project because the COVID-19 pandemic and the war in Ukraine have worsened economic and logistical conditions.
“Uncertainty and volatility in the global LNG market have made it difficult for Trans-Foreland to secure a suitable supply arrangement that would provide the financial certainty necessary for the project,” Trans-Foreland said in its filing.
Trans-Foreland has said the facility would import up to four tanker loads of LNG per year and use its boil-off gas management system to deliver imported gas to the adjacent Kenai Refinery.
The Kenai LNG export plant entered service in 1969. It has not exported LNG since 2015.
The plant was the only big LNG export facility in North America until Cheniere Energy Inc.’s LNG.A Sabine Pass export terminal in Louisiana entered service in February 2016. Nearly all of the LNG from Kenai went to Japan.
Recommended Reading
CEO: Coterra ‘Deeply Curious’ on M&A Amid E&P Consolidation Wave
2024-02-26 - Coterra Energy has yet to get in on the large-scale M&A wave sweeping across the Lower 48—but CEO Tom Jorden said Coterra is keeping an eye on acquisition opportunities.
E&P Earnings Season Proves Up Stronger Efficiencies, Profits
2024-04-04 - The 2024 outlook for E&Ps largely surprises to the upside with conservative budgets and steady volumes.
U.S. Shale-catters to IPO Australian Shale Explorer on NYSE
2024-05-04 - Tamboran Resources Corp. is majority owned by Permian wildcatter Bryan Sheffield and chaired by Haynesville and Eagle Ford discovery co-leader Dick Stoneburner.
Sunoco’s $7B Acquisition of NuStar Evades Further FTC Scrutiny
2024-04-09 - The waiting period under the Hart-Scott-Rodino Antitrust Improvements Act for Sunoco’s pending acquisition of NuStar Energy has expired, bringing the deal one step closer to completion.
TotalEnergies to Invest $400MM in LPG
2024-05-14 - TotalEnergies is investing more than $400 million into LPG to provide more than 100 million people in Africa and Asia access to clean cooking methods by 2030.