Norwegian operators Equinor and Vår Energi reported on Sept. 19 that costs for their offshore projects had increased significantly.
Costs for the Equinor-operated Johan Castberg have risen $1.2 billion (NOK 13 billion) in the last year, although it is still on track to begin production in the fourth quarter of 2024, while Vår Energi advised that capex for its operated Balder X project on the Norwegian Continental Shelf has risen by a further $340 million (NOK 3.6 billion) since the operator sounded the price increase alarm in September 2022.
A year ago, Vår cited increased scope of work, the continued impact from global supply chain challenges, COVID-19 and schedule change. Vår said the project required an additional gross investment of $1.2 billion (NOK 11.5 billion),bringing the total estimated gross project cost to $4.3 billion (NOK 40.7 billion). First oil from Balder X was delayed to third-quarter 2024, instead of late 2023.
Vår operates the Balder Field in PL001 with 90% interest on behalf of partner Mime Petroleum with 10% interest.
Vår is also a partner in the Johan Castberg project in 360 m to 390 m water depth in the Barents Sea.
That project has already faced problems, including a June 2021 citation by the Norwegian Petroleum Safety Authority of technical issues with the FPSO’s hull construction and an August 2022 fire on the FPSO.
When Equinor submitted the plan for development and operation (PDO) for Johan Castberg in 2017, the cost estimate was $5.3 billion (NOK 57 billion), but the updated project cost estimate increased to $7.4 billion (NOK 80 billion). Equinor said project costs jumped by $1.4 billion (NOK 15.5 billion) and that a currency effect of $651 million (NOK 7 billion) contributed to the price increase.
Infection control measures and reduced access to labor in connection with the COVID-19 pandemic affected the project, both in Singapore, where the hull and living quarters for the production vessel were constructed, and at Norwegian yards constructing modules for the production facility.
Geir Tungesvik, executive vice president for projects, drilling and procurement for Equinor, said project costs were “increasing due to a larger than expected scope of work and cost increases in the industry.”
In 2022, the Johan Castberg hull, including living quarters, was transported from Singapore to Stord for installation and commissioning. The main reason for the rise in the investment estimate from last year is that the workload transferred to Stord has been more comprehensive and complex than estimated, Equinor said. In addition, the project has not progressed as planned. Marine operations, drilling and completion costs have also increased.
Johan Castberg is a subsea project with 30 wells distributed on 10 templates and two satellites tied back to the Johan Castberg FPSO.
Proven volumes in Johan Castberg are estimated at between 450 MMbbl and 650 MMbbl of oil. The vessel is designed for production of close to 190,000 bbl/d.
Tungesvik said Johan Castberg is “still a good project with a solid economy” and a breakeven of about $35/bbl.
In 2022, two more discoveries were made that are considered for tie-back to Johan Castberg, and further exploration in the area is planned in the years ahead.
Equinor operates the project with 50% interest on behalf of partners Vår with 30% and Petoro AS with 20%.
Recommended Reading
Seatrium Awarded Contract for FPSO Bound for Guyana’s Stabroek
2024-05-17 - The topsides fabrication and integration contract will be for the FPSO Jaguar, bound for the Whiptail Field in the Stabroek block offshore Guyana for Exxon Mobil.
Third Suriname Find for Petronas, Exxon Could Support 100,000 bbl/d FPSO
2024-05-17 - A recent find offshore Suriname in Block 52 by Petronas and Exxon Mobil could support a 100,000 bbl/d FPSO development, according to Wood Mackenzie.
US Drillers Add Oil, Gas Rigs for First Time in Four Weeks: Baker Hughes
2024-05-17 - The oil and gas rig count rose by one to 604 in the week to May 17.
BPX Looks to Ramp US Production Over 60% by 2030
2024-05-16 - BPX Energy is looking to boost its U.S. production over 60% by 2030 as it considers bringing online a fourth processing facility in the Permian by mid-year 2025, Clark Edwards, the company’s vice president of development, said during SUPER DUG in Fort Worth.
Empire Petroleum’s Williston Drilling Program Identifies New Zones
2024-05-16 - Empire Petroleum provided updates on its Williston Basin development drilling program in its first quarter 2024 earnings results.