Talos Energy Inc. (NYSE: TALO) has started production ahead of schedule from its Mt. Providence subsea well located in the U.S. Gulf of Mexico’s Mississippi Canyon area, the company said July 19.
The company said the well began producing July 10, about 60 days before the originally planned completion date in early September. The well was drilled in January by Stone Energy Corp. prior to the closing of its merger with Talos.
“The combined Talos team completed the well and hooked it up to the 100% Talos owned Pompano platform in the company’s Mississippi Canyon complex within six months of concluding drilling operations,” Talos said in the release.
With a current gross production of 3,850 barrels of oil equivalent per day (boe/d), production is near the top of guidance of between 2,000 boe/d and 4,000 boe/d, the company said.
Recommended Reading
SM Energy Adds Brookman to Board, Promotes Lebeck to Executive VP
2024-02-23 - Barton R. Brookman previously served as President and CEO of PDC Energy and James B. Lebeck served as senior vice president and general counsel since January 2023.
Crescent Point Energy to Rebrand as Veren Inc.
2024-03-21 - The company will seek shareholder approval for the change at its upcoming annual and special meeting of shareholders on May 10.
Baker Hughes Declares Increased Quarterly Dividend
2024-02-02 - Baker Hughes’ dividend represents a 5% growth rate, or $0.01, over the previous quarter’s dividend.
NGL Growth Leads Enterprise Product Partners to Strong Fourth Quarter
2024-02-02 - Enterprise Product Partners executives are still waiting to receive final federal approval to go ahead with the company’s Sea Port Terminal Project.
enCore Energy Appoints Robert Willette as Chief Legal Officer
2024-02-01 - enCore Energy’s new chief legal officer Robert Willette has over 29 years of corporate legal experience.