A year-old bottleneck of crude in West Texas is shifting east as new pipelines prepare to begin operations without enough connections or storage for the smooth movement of shale oil to a U.S. Gulf Coast export hub, according to traders and analysts.
The U.S. exported a record 3.8 million barrels per day (MMbbl/d) of crude in late June after Congress lifted a 40-year export ban in late 2015. Soaring Permian crude output last year exceeded available pipeline space, creating a West Texas glut that knocked regional prices to the lowest levels in four years and helped spur a pipeline construction boom.
The start-up of three new pipelines by year-end from the Permian Basin was expected to bring about 2 MMbbl/d to export terminals around Corpus Christi. The prospect has narrowed the discount for Permian Basin oil compared with Brent to about $5.50 a bbl, down from about $8.50 in March.
But the rush to build pipelines largely outpaced construction of crude export docks and storage tanks in Corpus Christi, a timing mismatch that could create bottlenecks through the end of 2019, Barclays analysts said. They forecast the discount for Midland crude to Brent could widen again, to between $9 and $14 a bbl next year.
New oil pipelines typically are quick to fill as producer commitments and connections allow. However, at least one of the new lines, owned by EPIC Crude Pipeline LP, does not yet have all the connections and storage to handle the full 400,000 bbl/d capacity, sources said and regulatory filings released on July 1 show.
EPIC's line, which was converted to transport crude from natural gas liquids temporarily, has only filled about half of its initial capacity, and will move smaller-than-expected volumes when it begins service next month because of the lack of connections, according to nearly a dozen traders, brokers and others familiar with the company's operations.
EPIC declined to comment but in a regulatory filing on July 1 acknowledged it will provide only "minimal working tankage for storage" needed to move the oil. Some access and unloading points are either not yet in service or expected to be in service only by Aug. 15, the filing said.
The pipeline operator is in talks with NuStar Energy, which has a terminal at Corpus Christi, a NuStar spokesman confirmed. A deal could help address EPIC's storage shortfall as it works to construct its own terminal, traders said.
A second Permian oil pipeline that is expected to start operations late this year, Phillips 66's Gray Oak, also faces limited dock capacity in Corpus Christi, market sources said. Phillips 66 declined to comment other than to say it anticipates beginning service by year-end with connections to Corpus Christi refineries and export facilities.
EPIC, Phillips 66 and a third impending pipeline, Plains All American Pipeline LP's Cactus II, will be able use the largest export terminal near Corpus Christi, Moda Midstream LLC's Ingleside terminal. Moda has completed some of the tanks as part of the process of expanding storage to 12 MMbbl, with the full completion expected in 2020, a spokesman told Reuters.
Recommended Reading
Kimmeridge Fast Forwards on SilverBow with Takeover Bid
2024-03-13 - Investment firm Kimmeridge Energy Management, which first asked for additional SilverBow Resources board seats, has followed up with a buyout offer. A deal would make a nearly 1 Bcfe/d Eagle Ford pureplay.
Laredo Oil Subsidiary, Erehwon Enter Into Drilling Agreement with Texakoma
2024-03-14 - The agreement with Lustre Oil and Erehwon Oil & Gas would allow Texakoma to participate in the development of 7,375 net acres of mineral rights in Valley County, Montana.
SLB’s ChampionX Acquisition Key to Production Recovery Market
2024-04-21 - During a quarterly earnings call, SLB CEO Olivier Le Peuch highlighted the production recovery market as a key part of the company’s growth strategy.
Oil and Gas Chain Reaction: E&P M&A Begets OFS Consolidation
2024-04-26 - Record-breaking E&P consolidation is rippling into oilfield services, with much more M&A on the way.
Baker Hughes Awarded Saudi Pipeline Technology Contract
2024-04-23 - Baker Hughes will supply centrifugal compressors for Saudi Arabia’s new pipeline system, which aims to increase gas distribution across the kingdom and reduce carbon emissions