The first U.S. utility-scale offshore wind farm entered service on March 14 about 35 miles off the coast of Long Island, with the promise of generating enough power for about 70,000 homes at full capacity.
The 12-turbine, 130-megawatt South Fork Wind project is a joint venture between Denmark's Orsted and New England-based electric utility Eversource.
New York aims to reach 70% renewable energy by 2030 and to install nine gigawatts of offshore wind by 2035, and state Governor Kathy Hochul lauded the project as bringing it closer to those goals. "This is just the beginning of New York's offshore wind future," she said.
But the startup comes up at a time the offshore wind business has been plagued by rising costs tied to inflation, interest rates and supply chain constraints, forcing companies to write down assets and exit projects.
Eversource is one of a number of energy companies to recently announce it was exiting the offshore wind business. It plans to sell its stake in South Fork to Global Infrastructure Partners.
The uncertainty over offshore wind could jeopardize plans by U.S. President Joe Biden and several states, including New York, to meet their goals to decarbonize the power grid in an effort to fight back climate change.
Earlier this week, European energy firms Equinor and BP terminated their agreement to sell power to New York state from their proposed Empire Wind 2 offshore wind farm, citing rising costs and logistical challenges.
Recommended Reading
E&P Highlights: April 8, 2024
2024-04-08 - Here’s a roundup of the latest E&P headlines, including new contract awards and a product launch.
Electric Hype vs. Hydraulic Reality: Advantages of Traditional Systems
2024-05-07 - Castrol's new fluid prevents gas hydrates in deepwater control systems.
Deepwater Roundup 2024: Americas
2024-04-23 - The final part of Hart Energy E&P’s Deepwater Roundup focuses on projects coming online in the Americas from 2023 until the end of the decade.
Well Logging Could Get a Makeover
2024-02-27 - Aramco’s KASHF robot, expected to deploy in 2025, will be able to operate in both vertical and horizontal segments of wellbores.
Shell Brings Deepwater Rydberg Subsea Tieback Onstream
2024-02-23 - The two-well Gulf of Mexico development will send 16,000 boe/d at peak rates to the Appomattox production semisubmersible.