CNOOC Ltd. has brought onstream its Suizhong 36-1/Luda 5-2 project in the shallow waters of the Bohai Sea, the company said Feb. 5.
CNOOC’s operated Suizhong 36-1/Luda 5-2 oilfield secondary adjustment and development project is in water depths of about 30 m in Bohai Sea’s Liaodong Bay.
The main production facilities include two new central processing platforms and two new wellhead platforms. CNOOC plans 118 development wells, including 81 producers and 37 water injection wells. The project is expected to reach peak production of approximately 30,300 bbl/d in 2025.
CNOOC said this project represents the largest secondary development and adjustment project offshore China. The development relies on onshore power supply.
CNOOC Ltd. holds 100% interest in the project.
Recommended Reading
CEO: Coterra ‘Deeply Curious’ on M&A Amid E&P Consolidation Wave
2024-02-26 - Coterra Energy has yet to get in on the large-scale M&A wave sweeping across the Lower 48—but CEO Tom Jorden said Coterra is keeping an eye on acquisition opportunities.
CEO: Magnolia Hunting Giddings Bolt-ons that ‘Pack a Punch’ in ‘24
2024-02-16 - Magnolia Oil & Gas plans to boost production volumes in the single digits this year, with the majority of the growth coming from the Giddings Field.
Endeavor Integration Brings Capital Efficiency, Durability to Diamondback
2024-02-22 - The combined Diamondback-Endeavor deal is expected to realize $3 billion in synergies and have 12 years of sub-$40/bbl breakeven inventory.
Patterson-UTI Braces for Activity ‘Pause’ After E&P Consolidations
2024-02-19 - Patterson-UTI saw net income rebound from 2022 and CEO Andy Hendricks says the company is well positioned following a wave of E&P consolidations that may slow activity.
E&P Earnings Season Proves Up Stronger Efficiencies, Profits
2024-04-04 - The 2024 outlook for E&Ps largely surprises to the upside with conservative budgets and steady volumes.