The state of Western Australia has ordered an inquiry into a delay in burying carbon dioxide emissions at Chevron Corp.’s (NYSE: CVX) Gorgon LNG project, which could lead to a change in conditions on the project, on May 10.
The state approved the $54 billion Gorgon project in 2009 on the condition that at least 80% of carbon dioxide released in its gas processing operations over a five-year rolling average period would be buried.
“It has become apparent there needs to be a clearly defined start point for the commencement of the five-year rolling average,” Stephen Dawson, the state environment minister, told reporters in the Perth, the state capital, on May 7, according to an email sent to Reuters by his spokeswoman.
He ordered the state’s Environmental Protection Authority to report back within the next nine months whether the conditions should be changed, along with any other recommendations.
Chevron said it welcomed the review “to clarify the existing condition” on the carbon capture project.
“Our focus is on the safe commissioning and start-up of the carbon dioxide injection project and achieving a high percentage of injection over the 40-year life of the Gorgon project,” a Chevron spokeswoman said in emailed comments.
Chevron told the government last December it would not be able to start capturing and burying carbon dioxide until the fourth-quarter of 2018 at the earliest, after having found problems with valves and pipeline equipment during commissioning of its AU$2.5 billion (US$1.9 billion) injection system.
The Gorgon carbon dioxide injection system is the world’s largest capture and storage project.
Processing operations began in March 2016, when Gorgon started producing gas from the Jansz field.
However, Chevron only intended to start burying carbon dioxide after it started producing from the Gorgon field, which has a higher carbon dioxide content. Production started there in 2017.
Gorgon LNG is owned by Chevron, ExxonMobil Corp. (NYSE: XOM), Royal Dutch Shell (NYSE: RDS.A), and Japan’s Osaka Gas, Tokyo Gas and JERA.
Recommended Reading
Rhino Taps Halliburton for Namibia Well Work
2024-04-24 - Halliburton’s deepwater integrated multi-well construction contract for a block in the Orange Basin starts later this year.
Halliburton’s Low-key M&A Strategy Remains Unchanged
2024-04-23 - Halliburton CEO Jeff Miller says expected organic growth generates more shareholder value than following consolidation trends, such as chief rival SLB’s plans to buy ChampionX.
Deepwater Roundup 2024: Americas
2024-04-23 - The final part of Hart Energy E&P’s Deepwater Roundup focuses on projects coming online in the Americas from 2023 until the end of the decade.
Ohio Utica’s Ascent Resources Credit Rep Rises on Production, Cash Flow
2024-04-23 - Ascent Resources received a positive outlook from Fitch Ratings as the company has grown into Ohio’s No. 1 gas and No. 2 Utica oil producer, according to state data.
E&P Highlights: April 22, 2024
2024-04-22 - Here’s a roundup of the latest E&P headlines, including a standardization MoU and new contract awards.